Logo

Bulk Data Centers unveils plan for data centre expansion

Bulk Data Centers launches a new major data center facility at the N01 Data Center Campus in Southern Norway, with the Campus’ existing capacity contracted due to surging market demand.

Bulk Data Centers says that construction has commenced of a new 42MW data center facility scheduled for completion this year.

“The rapid growth in occupancy at the N01 Data Center Campus underscores the undeniable demand for highly scalable, cost-effective, and sustainable solutions. The success of our strategic approach is reflected in the trust from our owners and partners, which will help us to build data centers of the future that meet the demands of our growing customer base,” said Gisle M. Eckhoff, Executive Vice President, Bulk Data Centers at Bulk Infrastructure.

The new facility will offer 42MW of IT space, designed to accommodate the latest generation of high-density GPU and CPU infrastructure. It will include air cooling and direct liquid cooling capabilities of up to 100kW+ per rack.

This is on the back of the successful launch of a 12MW data center facility at the N01 Data Center Campus, which was ready for service in 2023 and is now fully contracted due to high demand.

Scaling with focus on low-cost and sustainability

The new 42MW facility will be constructed at the 300-hectare site and connect to the existing 125MVA dual onsite sub-stations.

In addition to the current construction-ready levelled land area of 265,000 sqm, Bulk will also undertake the preparation of an additional 300,000 sqm to facilitate future expansion of the data center facilities.

Bulk Data Centers takes a long-term strategic approach in the site master planning, combined with innovative proven colocation designs to reduce lead time and enable the fastest time to market.

“Meeting our customers' demands is our number one priority. Our team possesses an intimate knowledge of market trends, and we remain dedicated to constructing data center infrastructure at a large scale and in the shortest timeframes. At a time when countries across Europe are facing constraints on land and power, we offer a holistic solution, enabling our customers to scale in a low-cost sustainable way,” says Rob Elder, Chief Commercial Officer at Bulk Data Centers.

As part of the longer-term scaling at the N01 Data Center Campus, Bulk is working jointly with regional and national grid companies to add 300MW of additional, redundant power capacity that allows for continued large scale data center expansion, both for hyperscale and colocation facilities.

The N01 Data Center Campus has the potential to grow beyond 1000MW supported by a strategic location in immediate proximity to one of Northern Europe’s largest transformer stations and 300 hectares of zoned land. The site has access to surplus production of 100% renewable power and is highly connected with large-capacity intercontinental and regional fiber routes, connecting the site directly to European and North American transport hubs.

Antti “Jogi” Poikola takes charge of FDCA to strengthen Finland's data centre industry.
Angel Business Communications has announced the launch of the Data Centre Solutions Roadshow, a new...
Alerify partners with Zadara and aims to enhance AI capabilities while ensuring data privacy and...
Vertiv’s Next Predict service uses AI to monitor data centre equipment and provide predictive...
XYZ Reality appoints Bruno P.S. Rocha as COO and Soroosh Keshtgar as CFO, positioning the company...
Advania retains its VMware Cloud Service Provider status, continuing to support private cloud and...
Portus Data Centers has appointed Richard Pimper as its Chief Operating Officer and Chief...
Patmos Hosting has secured a $100 million C-PACE loan to redevelop the former Kansas City Star...